Current Construction Projects

 

Project Project Number % Complete Awarded Contract Contractor
Northwest Road Improvements 15-04-RC 30% $2,512,085.49 D Construction
EWWWTP Clarifier 15-25-WW 0% $1,176,900.00 Leander Construction, Inc.
Mausoleum Rehab 15-33-CM 77% $222,937.00 Multiple
Splash Park 16-18-SP 20% $1,796,711.25 Multiple
Marathon Gas Demo-Building 16-23-DM 95% $19,899.00 Scanlon Excavating & Concrete, Inc.
Marathon Gas Demo-Tank Pull 16-23-DM 95% $23,489.32 Purpose Contracting, Inc.
2017 General Fund Street Program 17-02-RS 95% $452,336.91 Universal Asphalt & Excavating, Inc.
Area 3 Phase 2 Sewer Separation 17-03-SS 25% $1,349,958.24 SKI Sealcoating & Maintenance, Inc.
2017 MFT 17-04-RS 0% n/a n/a
McKinley Park Concession 17-05-BG 0% $148,935.00 H & H Builders
Area 3 Phase 1 Sewer Separation 16-03-SS 98% $1,195,240.00 J.W. Ossola Co.
Water St. Road Improvements 15-08-RC 100% $256,161.45 Advanced Asphalt